πŸ“‹ Case Study

110 kV Substation Expansion Study

Voltage drop exceeding 5% at downstream feeders; insufficient reactive support during peak summer load

πŸ—οΈ Project Overview

Expansion of regional 110 kV GIS substation serving growing urban load center

🎯 Challenge

Voltage drop exceeding 5% at downstream feeders; insufficient reactive support during peak summer load

πŸ”§ Design Approach

Integrated VAR compensation via 12 MVAR STATCOM + revised tap settings on 110/33 kV transformers; updated Y-Bus with new feeder impedances

πŸ“ Design Diagram

110 kV Substation Expansion Study Voltage drop >5% | Insufficient reactive support (peak summer) 110 kV Bus 110/33 kV Tap: 1.025 pu STATCOM +12 MVAR 33 kV Feeders βˆ‚V_i/βˆ‚Q_j = -0.018 p.u./MVAR Updated Y-Bus with new feeder impedances Bus / Line Transformer STATCOM Challenge

AI-generated project design illustration

πŸ“ Key Calculations

Voltage Profile Sensitivity (dV/dQ)

βˆ‚V_i/βˆ‚Q_j = Re(Y⁻¹)_ij
Result: -0.018 p.u./MVAR
Guided STATCOM placement at weakest bus (Bus #42)

Transformer Tap Optimization

V_out = V_in Γ— (N_tap / N_nom)
Result: 1.025 pu tap ratio selected
Restored 33 kV bus voltage to 1.002 p.u. under peak load

πŸ“Š Results

Voltage deviation reduced from βˆ’6.2% to +0.8%; transformer loading decreased by 14%; STATCOM utilization < 65% across all scenarios

πŸ’‘ Lessons Learned

  • β€’STATCOM location must be validated using Q-V curvesβ€”not just voltage magnitude
  • β€’Tap scheduling requires co-optimization with capacitor banks

βœ… Key Takeaways

  • 1STATCOM location must be validated using Q-V curvesβ€”not just voltage magnitude
  • 2Tap scheduling requires co-optimization with capacitor banks